第1题
Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A . 2
B . 3
C . 4
D . 5
E . 7
第2题
● Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A 2
B 3
C 4
D 5
E 7
第3题
120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A. 2
B. 3
C. 4
D. 5
E. 7
第4题
2 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A. 2
B. 3
C. 4
D. 5
E. 7
第5题
● Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A 0
B 1
C 2
D 3
E 4
第6题
● Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A 11, 13
B 12, 14
C 13, 15
D 14, 16
E 15, 17
第7题
193 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A. 0
B. 1
C. 2
D. 3
E. 4
第8题
111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A. 0
B. 1
C. 2
D. 3
E. 4
第9题
1 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.
A. 2, 10
B. 4, 12
C. 6, 14
D. 7, 15
E. 9, 17
第10题
199 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A. 11, 13
B. 12, 14
C. 13, 15
D. 14, 16
E. 15, 17