● Using the figure in the Special window, The Critical path is _____ weeks.
A 21
B 22
C 23
D 24
E 25
第2题
● Using the figure in the Special window, The critical path is:
A A-B-G
B C-G
C C-D
D E-F
E A-B-G and C-D
第3题
Using the figure in the Special window, The critical path is:
A . A-B-G
B . C-G
C . C-D
D . E-F
E . A-B-G and C-D
第4题
Using the figure in the Special window, The Critical path is _____ weeks.
A . 21
B . 22
C . 23
D . 24
E . 25
第5题
Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A . 2
B . 3
C . 4
D . 5
E . 7
第6题
Using the figure in the Special Window, what is the probability of success for Project B?
A 0.3
B 0.2
C 0.35
D 0.15
E 0.12
第7题
200 Using the figure in the Special Window, what is the probability of success for Project B?
A. 0.30
B. 0.20
C. 0.35
D.0.15
E.0.12
第8题
114 Using the figure in the Special window, The Critical path is _____ weeks.
A. 21
B. 22
C. 23
D. 24
E. 25
第9题
120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A. 2
B. 3
C. 4
D. 5
E. 7
第10题
110 Using the figure in the Special window, The critical path is:
A. A-B-G
B. C-G
C. C-D
D. E-F
E. A-B-G and C-D