第1题
144 Free float is the amount of time that an activity may be delayed with out affecting the _____.
A. Early start of the succeeding activities.
B. Late start of the succeeding activities.
C. Project finish.
D. Cost of the project.
E. None of the above
第2题
26 Free float is the amount of time that an activity may be delayed with out affecting the _____.
A. Early start of the succeeding activities.
B. Late start of the succeeding activities.
C. Project finish.
D. Cost of the project.
E. None of the above
第3题
A.Early start of the succeeding activities.
B.Late start of the succeeding activities.
C.Project finish.
D.Cost of the project.
E.None of the above.
第4题
● The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF).
D Scheduled time (LF - ES).
E Event.
第5题
35 The range of time allowed for an activity to be completed in is the _____.
A. Planned time (Duration).
B. Float time (LS - ES, or LF - EF).
C. Critical time (when ES = LS, or EF = LF).
D. Scheduled time (LF - ES).
E. Event.
第6题
153 The range of time allowed for an activity to be completed in is the _____.
A. Planned time (Duration).
B. Float time (LS - ES, or LF - EF).
C. Critical time (when ES = LS, or EF = LF).
D. Scheduled time (LF - ES).
E. Event
第7题
A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
第8题
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
第9题
It is proved that the uncontrolled activity of free radicals caused many cancers.
A.Y
B.N
C.NG
第10题
A.Planned value
B.Actual cost
C.Earned value
D.Cost variance