![](https://lstatic.shangxueba.com/sxbzda/h5/images/m_q_title.png)
对资源税代理纳税审查下列表述中正确的有()。
A.纳税人开采或生产应税矿产品销售的以销售数量为课税数量
B.纳税人开采或生产应税矿产品自用的以自用数量为课税数量,自用是指非生产自用,不包括生产自用部分
C.企业收购未税矿产品未履行代扣代缴义务应承担补税的责任
D.独立矿山铁矿石资源税减按40%征收
E.资源税的纳税人是在我国境内从事开采应税矿产品和生产盐的单位和个人
![](https://lstatic.shangxueba.com/sxbzda/h5/images/tips_org.png)
A.纳税人开采或生产应税矿产品销售的以销售数量为课税数量
B.纳税人开采或生产应税矿产品自用的以自用数量为课税数量,自用是指非生产自用,不包括生产自用部分
C.企业收购未税矿产品未履行代扣代缴义务应承担补税的责任
D.独立矿山铁矿石资源税减按40%征收
E.资源税的纳税人是在我国境内从事开采应税矿产品和生产盐的单位和个人
第1题
A.relationships
B.resources
C.stakeholders
D.deliverables
第2题
A.cost management planB.risk management planC.scope management planD.management schedule
第3题
Deflection involves the transfer of risk by:
A Contracting out to another party
B Developing schedule alternative.
C Establishing functions under the project manager to handle risk events.
D Disaster planning and responses.
E None of the above.
第4题
156 Deflection involves the transfer of risk by:
A. Contracting out to another party
B. Developing schedule alternative.
C. Establishing functions under the project manager to handle risk events.
D. Disaster planning and responses.
E. None of the above
第5题
38 Deflection involves the transfer of risk by:
A. Contracting out to another party
B. Developing schedule alternative.
C. Establishing functions under the project manager to handle risk events.
D. Disaster planning and responses.
E. None of the above
第6题
The primary source document for establishing the content of the Project Status Report is:
A The project charter
B The Project Plan
C The ASTM Project Document Guide
D The summary work breakdown structure
第7题
176 The primary source document for establishing the content of the Project Status Report is:
A. The project charter
B. The Project Plan
C. The ASTM Project Document Guide
D. The summary work breakdown structure
第8题
94 The primary source document for establishing the content of the Project Status Report is:
A. The project charter
B. The Project Plan
C. The ASTM Project Document Guide
D. The summary work breakdown structure
第9题
The(72)technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.
A.Cost Aggregation
B.Reserve Analysis
C.Parametric Estimating
D.Funding Limit Reconciliation