A company has the following production planned for the next four weeks. The figures reflec
The direct labour force is threatening to go on strike for two weeks out of the coming four. This means that only 2,160 hours will be available for production rather than the usual 4,320 hours.
If the strike goes ahead, which product or products should be produced if profits are to be maximised?
A.D and A
B.B and D
C.D only
D.B and C