●During the planning phase of a project, you realize that more than one functional departm
● During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:
A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B Let the affected line groups decide among themselves who will perform. the work
C Ask the executive sponsor to make the decision
D Allow each line group to perform. part of the task
E All of the above