47During the planning phase of a project, you realize that more than one functional depart
47 During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:
A. Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B. Let the affected line groups decide among themselves who will perform. the work
C. Ask the executive sponsor to make the decision
D. Allow each line group to perform. part of the task
E. All of the above