105A budget estimate should give the manager cost data accurate to within: A.-5 to +10 per
105 A budget estimate should give the manager cost data accurate to within:
A. -5 to +10 percent of actual cost
B. -25 to +75 percent of actual cost
C. -30 to +75 percent of actual cost
D. -10 to +25 percent of actual cost
E. None of the above