Range estimating in determining cost risk probabilities requires _____ .
A an amount of financial exposure.
B risks and opportunities ranked in order of bottom line importance
C contingency requirements for expected level of confidence
D probability of cost overrun occurrences
E All of the above.
第2题
19 Range estimating in determining cost risk probabilities requires _____ .
A. an amount of financial exposure.
B. risks and opportunities ranked in order of bottom line importance
C. contingency requirements for expected level of confidence
D. probability of cost overrun occurrences
E. All of the above
第3题
84 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above.
第4题
In which of the following cost estimating techniques are statistics models used:
A . nonparametric cost estimating
B . parametric cost estimating
C . life cycle cost estimating
D . bottom-up estimating
E . All of the above.
第5题
166 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above
第6题
Cost management includes:
A . Cost estimating/forecasting.
B . Cost budgeting/cost control.
C . Cost applications.
D . All of the above.
E . A and B only.
第7题
98 Cost management includes:
A. Cost estimating/forecasting.
B. Cost budgeting/cost control.
C. Cost applications.
D. All of the above.
E. A and B only
第8题
180 Cost management includes:
A. Cost estimating/forecasting.
B. Cost budgeting/cost control.
C. Cost applications.
D. All of the above.
E. A and B only
第9题
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
空白(1)处填()
A. accuracy
B. approximation
C. specification
D. summary
第10题
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
A.accuracy
B.approxination
C.specification
D.summary