The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第2题
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第3题
2 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments
第4题
The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating
第5题
The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating
第6题
The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A.Time, schedule and cost.
B.Management coordination and organization structuring.
C.Work methods and accountability.
D.Quality of work.
E.Risk and impact decision-making.
第7题
The work breakdown structure (WBS) has been widely used in management for software development project, () is generally NOT validated through the WBS.
A.Schedule and cost
B.Organization structuring
C.Management coordination
D.Quality of work
第8题
What is the purpose of the work breakdown structure (WBS)?
A.The WBS allows the project manager to delegate responsibility of all of the project activities
B.The WBS is a narrative description of the work required for the project
C.The WBS describes the total program as a summation of subdivided elements
D.The WBS is a statement of what will be made, how many units will be made, and when they will be made
第9题
● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .
(72)
A.identifying individual tasks for a project
B.scheduling the start of tasks
C.scheduling the end of tasks
D.determining potential delays
第10题
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.