第1题
In the arrow diagramming method (ADM), _____ do not consume time or resources.
A.Events.
B.Activities
C.Slack elements.
D.B and C only.
E.All of the above.
第2题
17 In the arrow diagramming method (ADM), _____ do not consume time or resources.
A. Events.
B. Activities
C. Slack elements.
D. B and C only.
E. All of the above
第4题
The most frequently used construct in Precedent Diagramming Method is:
A.Start to Start.
B.Finish to Finish.
C.Start to Finish.
D.Finish to Start.
E.Dummy activity.
第5题
● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.
(75)
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第6题
● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.
(75)
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第7题
● The most frequently used construct in Precedent Diagramming Method is:
A Start to Start.
B Finish to Finish.
C Start to Finish.
D Finish to Start.
E Dummy activity.
第8题
194 The most frequently used construct in Precedent Diagramming Method is:
A. Start to Start.
B. Finish to Finish.
C. Start to Finish.
D. Finish to Start.
E. Dummy activity
第9题
76 The most frequently used construct in Precedent Diagramming Method is:
A. Start to Start.
B. Finish to Finish.
C. Start to Finish.
D. Finish to Start.
E. Dummy activity
第10题
Tool for defining activities is().
A.Dependency Determination
B.Precedence Diagramming method
C.Rolling Wave Planning
D.Schedule network Templates