● Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
第2题
42 Which of the following impacts the critical path?
A. Changing the task duration.
B. Reduce the free float of an activity.
C. Executing a backward pass
D. A or B
E. None of the above
第3题
160 Which of the following impacts the critical path?
A. Changing the task duration.
B. Reduce the free float of an activity.
C. Executing a backward pass
D. A or B
E. None of the above
第4题
A.Critical path is the longest path in the project network
B.Critical path shows the shortest duration of the project
C.Critical path is unique
D.Determines the overall project duration
第5题
In the following statements about graph operations,which one is NOT correct?
A.Finding critical path is an operation on directed graph
B.Finding critical path is an operation on undirected graph
C.Spanning tree of a graph may not be unique
D.Minimum spanning tree of a graph may not be unique
第6题
Which of the following situations did Hayden face at Critical Path in 2001?
A.The employees were worried about job security.
B.The investors were calling for changes to the company structure.
C.The management was misleading the staff about the company's position.
D.The board of directors did not realise the scale of the company's problems.
第7题
A project element which lies between two events is called:
A.An activity.
B.A critical path method.
C.A slack milestone.
D.A timing slot.
E.A calendar completion point.
第8题
The critical path is calculated by
A.subtracting the end date of task one from the start date of task two.
B.determining which tasks have the least amount of total slack.
C.totaling the time for all activities.
D.determining the shortest path through the network.
E.Determining which tasks have the most slack
第9题
Which of the following is indicative of negative float?
A.The late start date is earlier than the early start date.
B.The critical path supports the imposed end date.
C.The early finish date is equal to the late finish date.
D.When leads are employed in the schedule.
E.The project is sinking.
第10题
The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.