The process of()schedule activity durations uses information on schedule activityscope of
A.estimating
B.defining
C.planning
D.sequencing
A.estimating
B.defining
C.planning
D.sequencing
第1题
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第2题
A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
第3题
In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter
第4题
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development