is a method of constructing a project schedule network diagram that uses boxes or rect
angles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.
A.PDM
B.CPM
C.PERT
D.AOA