● (73) is a method used in Critical Path Methodology for constructing a project schedule n
etwork diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between
them.
(73)
A.PERT
B.AOA
C.WBS
D.PDM