第1题
154 Which of the following is not part of contract administration
A. contract award
B. performance control
C. financial control
D. contract closeout
E. All of the above are parts of contract administration
第2题
36 Which of the following is not part of contract administration
A. contract award
B. performance control
C. financial control
D. contract closeout
E. All of the above are parts of contract administration
第3题
Which of the following is not part of the acquisition process:
A source selection
B invitation to bid
C contract award
D notice to proceed
E All of the above are parts of the acquisition process.
第4题
A.cd /adm
B. cd ./adm
C. cd ../adm
D. cd /../adm
第5题
30 Which of the following is not part of the acquisition process:
A. source selection
B. invitation to bid
C. contract award
D. notice to proceed
E. All of the above are parts of the acquisition process
第6题
Which of the following terms represents a contract type category?
A.Fixed-price
B.Cost-reimbursement
C.Unit-price
D.a & b
E.a, b, & c
第7题
176 The definitive terms of a contract are written during which of the following contract phases? A. Contract Phase
B. Post-Award Phase
C. Award Phase
D. Pre-Award Phase
E. Requirement Phase
第8题
94 The definitive terms of a contract are written during which of the following contract phases? A. Contract Phase
B. Post-Award Phase
C. Award Phase
D. Pre-Award Phase
E. Requirement Phase
第9题
Which of the following is equivalent to a lump sum contract:
A fixed price contract
B price fixing contract
C purchase order
D All of the above.
E B and C only